  1. Newsgroups: sci.space.news
  2. Path: coplex.coplex.com!uunet!elroy.jpl.nasa.gov!ames!dont-send-mail-to-path-lines
  3. From: yee@atlas.arc.nasa.gov (Peter Yee)
  4. Subject: STS-57 countdown scheduled to begin June 17  [Release 66-93] (Forwarded)
  5. Message-ID: <1993Jun16.223537.26141@news.arc.nasa.gov>
  6. Apparently-To: sci-space-news@ames.arc.nasa.gov
  7. Followup-To: sci.space
  8. Originator: yee@atlas.arc.nasa.gov
  9. Sender: usenet@news.arc.nasa.gov
  10. Reply-To: yee@atlas.arc.nasa.gov (Peter Yee)
  11. Organization: NASA Ames Research Center, Moffett Field, CA
  12. Date: Wed, 16 Jun 1993 22:35:37 GMT
  13. Approved: sci-space-news@ames.arc.nasa.gov
  14. Lines: 380
  15.  
  16.           Bruce Buckingham
  17.           407/867-2468                                      June 16, 1993
  18.  
  19.           KSC Release No. 66 - 93
  20.  
  21.  
  22.           STS-57 COUNTDOWN SCHEDULED TO BEGIN JUNE 17 
  23.  
  24.                The countdown to launch Space Shuttle Endeavour on mission
  25.           STS-57 is scheduled to begin at 2:30 a.m. EDT on Thursday, June
  26.           17, at the T-43 hour mark. This will be the fourth launch of the
  27.           orbiter Endeavour and the 56th overall in the Space Shuttle
  28.           program. The countdown includes 36 hours and 3 minutes of
  29.           built-in hold time leading to the opening of the launch window at
  30.           9:38 a.m. (EDT) on Sunday, June 20. The launch window extends
  31.           until 10:49 p.m.
  32.  
  33.                A primary objective of this mission is the retrieval of the
  34.           European Space Agency's free-flying platform, EURECA. This
  35.           spacecraft was deployed from the Shuttle on mission STS-46,
  36.           launched on July 31, 1992. EURECA is primarily a microgravity
  37.           mission specifically designed for material processing and life
  38.           sciences payloads. Endeavour's crew will grapple the platform and
  39.           return with it to Earth.
  40.  
  41.                Endeavour will carry into orbit the commercial spacelab
  42.           facility called SPACEHAB, a small pressurized module situated in
  43.           the forward section of Endeavour's payload bay. It was designed
  44.           by the privately financed corporation, SPACEHAB, Inc.
  45.  
  46.                Also in the payload bay are several other experiments
  47.           including the Super Fluid Helium on Orbit Transfer (SHOOT)
  48.           Demonstration experiment and ten Get-Away Specials (GAS)
  49.           experiments. Another of Endeavour's mission objectives is to
  50.           allow two of the astronauts to perform a spacewalk for training
  51.           and practice of deploy and retrieval techniques which will
  52.           support Space Station assembly and the Hubble telescope servicing
  53.           mission.
  54.  
  55.                At the beginning of the countdown, the KSC launch team in
  56.           Firing Room 3 of the Launch Control Center will verify systems
  57.           indicating the Shuttle is powered up and that the data processing
  58.           and backup flight control systems are operating trouble free.
  59.  
  60.                Verifications will occur throughout the count to ensure
  61.           reviews of the flight software stored in the orbiter's twin
  62.           memory banks is being conducted, computer controlled display
  63.           systems are being activated, and the backup flight system general
  64.           purpose computer is being loaded.
  65.  
  66.                This week, final ordnance operations were conducted at the
  67.           pad and the orbiter's aft engine compartment was closed for
  68.           flight on Tuesday. Following countdown commencement at 2:30 a.m.
  69.           Thursday, operations will begin to prepare the main propulsion
  70.           system and the orbiter's main engines for cryogenic loading.
  71.           Orbiter navigation aids will be turned on and tested and the
  72.           inertial measurement units will be activated.
  73.  
  74.                Also on Thursday, ground crews will begin making the final
  75.           storage of mid-deck and flight deck supplies and payloads. They
  76.           will also perform microbial samplings of the flight crew's
  77.           drinking water and check water levels in the crew waste
  78.           management system.
  79.  
  80.                At T-27 hours, the countdown will enter its first built-in
  81.           hold. This is an eight hour hold lasting from 6:30 p.m. Thursday
  82.           to 2:30 a.m. Friday.
  83.  
  84.                When the countdown resumes, the launch pad will be cleared
  85.           of all personnel in preparation for cryogenic fuel loading of the
  86.           power reactant and storage distribution system tanks located
  87.           under the payload bay lining. These tanks hold the super-cold
  88.           liquid hydrogen and liquid oxygen reactants used by the fuel
  89.           cells to provide electricity to the orbiter and drinking water
  90.           for the crew.
  91.  
  92.                Cryogenic flow is scheduled to start at about 2:30 a.m. and
  93.           continue for about eight hours.
  94.  
  95.                As servicing of the cryogenic tanks concludes, the clock
  96.           will enter another built-in hold at the T-19 hour mark. This hold
  97.           will last for four hours from 10:30 a.m. to 2:30 p.m. on Friday.
  98.  
  99.                Following cryogenic loading operations, the pad will be
  100.           reopened for normal work and the orbiter mid-body umbilical unit
  101.           used to load the super-cold reactants in the orbiter's fuel cell
  102.           tanks will be demated and retracted into the launch structure.
  103.  
  104.                When the countdown resumes, technicians will complete final
  105.           vehicle and facility closeouts and begin activating the orbiter's
  106.           communications systems and configuring Endeavour's cockpit for
  107.           flight. The orbiter's flight control system and navigation aids
  108.           will be activated. The stowable crew seats will be installed in
  109.           the flight and mid-decks.
  110.  
  111.                The countdown will enter a built-in hold at the T-11 hour
  112.           mark at 10:30 p.m. Friday. This 20 hour, 43 minute hold will last
  113.           until 7:13 p.m. Saturday. During this hold, time critical
  114.           equipment will be installed in the orbiter's cockpit and the
  115.           inertial measurement units will be activated and warmed up. Also,
  116.           late stowage operations in the SPACEHAB module will be conducted.
  117.  
  118.                At about 11:00 a.m. Saturday, the Rotating Service Structure
  119.           is scheduled to be moved away from the vehicle and placed in
  120.           launch position.
  121.  
  122.                At T-9 hours, about 9:13 p.m. Saturday, the onboard fuel
  123.           cells will be activated. At T-8 hours, the launch team will begin
  124.           evacuating the blast danger area and clear the pad for loading
  125.           the external tank with the super-cold cryogenic fuels. At T-7
  126.           hours, 30 minutes, conditioned air that is flowing through the
  127.           orbiter's payload bay and other areas on the orbiter will be
  128.           switched to gaseous nitrogen in preparation for fueling the
  129.           external tank. The inertial measurement units will transition
  130.           from the warm up stage to the operate/attitude determination mode
  131.           at T-6 hours, 45 minutes.
  132.  
  133.                The countdown will enter another planned built-in hold at
  134.           the T-6 hour mark at 12:13 a.m. Sunday. During this one-hour
  135.           hold, final preparations for loading the external tank will be
  136.           completed and a pre-tanking weather briefing will be conducted.
  137.  
  138.                Chilldown of the lines that carry the cryogenic propellants
  139.           to the external tank begins when the clock starts counting again
  140.           at 1:13 a.m. Filling and topping off the external tank should be
  141.           complete at the beginning of the next planned hold at T-3 hours,
  142.           or 4:13 a.m. Sunday.
  143.  
  144.                During the two-hour hold at T-3 hours, an ice inspection
  145.           team will conduct a survey of the external tank's outer
  146.           insulation and other Shuttle components. Also, the closeout crew
  147.           will be dispatched to the pad and begin configuring the crew
  148.           module and white room for the flight crew's arrival. Liquid
  149.           oxygen and liquid hydrogen will be in a stable replenish mode
  150.           during this time to replace any propellant that "boils" off.
  151.  
  152.                Prior to entering the hold at T-3 hours, the six-member
  153.           STS-57 crew will be awakened at about 3:03 a.m. Sunday.
  154.  
  155.                Following breakfast, the crew will receive a briefing on
  156.           weather conditions both at KSC and around the world via satellite
  157.           from Mission Control, Houston.
  158.  
  159.                The flight crew will suit-up in their partial-pressure
  160.           suits, then leave the Operations and Checkout Building during the
  161.           T-3 hour hold, or at about 6:08 a.m. They will arrive at the
  162.           pad's white room at about 6:38 a.m. where they will be assisted
  163.           by white room personnel in getting into the crew cabin.
  164.  
  165.                Just prior to the T-1 hour mark, the test team and the
  166.           flight crew will get another weather update, including
  167.           observations from an astronaut flying in a Shuttle Training
  168.           Aircraft in the KSC area.
  169.  
  170.                They will also be briefed as to the exact location of the
  171.           EURECA spacecraft and the specific launch time may be adjusted by
  172.           as much as a few minutes. Any additional hold time necessary to
  173.           compensate for this change will be added to the final hold at T-9
  174.           minutes.
  175.  
  176.                The last two built-in holds will be 10 minutes in duration
  177.           (with the exception that the hold at T-9 minutes could be
  178.           adjusted to compensate for the location of EURECA) and will occur
  179.           at the T-20 minute mark, or at 8:53 a.m. and at the T-9 minutes
  180.           mark at 9:14 a.m. During the final hold, the flight crew and
  181.           ground team receive the NASA launch director's and the mission
  182.           management team's final "go" for launch.
  183.  
  184.                Milestones after the T-9 minute mark include start of the
  185.           ground launch sequencer; retraction of the orbiter access arm at
  186.           T-7 minutes, 30 seconds; start of the orbiter's auxiliary power
  187.           units at T-5 minutes; pressurization of the liquid oxygen tank
  188.           inside the external tank at T-2 minutes, 55 seconds;
  189.           pressurization of the liquid hydrogen tank at T-1 minute, 57
  190.           seconds; and the electronic "go" to Endeavour's onboard computers
  191.           to start their own terminal countdown sequence at T-31 seconds.
  192.           The orbiter's three main engines will start at T-6.6 seconds.
  193.  
  194.           ZDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDD?
  195.           3                      COUNTDOWN MILESTONES                     3
  196.           @DDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDY
  197.  
  198.                          Launch - 3 Days (Thursday, June 17)
  199.  
  200.                Prepare for the start of the STS-57 launch countdown and
  201.           perform the call-to-stations at the T-43 hour mark. Countdown
  202.           will begin at 2:30 a.m. All members of the launch team will
  203.           report to their respective consoles in Firing Room 3 in the
  204.           Launch Control Center for the start of the countdown.
  205.  
  206.                Enter the first planned built-in hold at T-27 hours for a
  207.           duration of eight hours.
  208.  
  209.                Check out back-up flight system and review flight software
  210.           stored in mass memory units and display systems. Load backup
  211.           flight system software into Endeavour's general purpose
  212.           computers.
  213.  
  214.                Begin stowage of flight crew equipment. Inspect the
  215.           orbiter's mid-deck and flight-deck and remove crew module
  216.           platforms. Start external tank loading preparations and prepare
  217.           the Shuttle's main engines for main propellant tanking and
  218.           flight.
  219.  
  220.                           Launch - 2 Days (Friday, June 18)
  221.  
  222.                Resume countdown. Start preparations for servicing fuel cell
  223.           storage tanks and begin final vehicle and facility closeouts for
  224.           launch.
  225.  
  226.                Clear launch pad of all personnel and begin loading liquid
  227.           oxygen and liquid hydrogen reactants into Endeavour's fuel cell
  228.           storage tanks.
  229.  
  230.                After loading operations, the pad will be reopened for
  231.           normal work. Orbiter and ground support equipment closeouts will
  232.           resume.
  233.  
  234.                Enter planned built-in hold at T-19 hours for a duration of
  235.           4 hours.
  236.  
  237.                Demate orbiter mid-body umbilical unit. Resume countdown.
  238.  
  239.                Activate orbiter communications systems, flight control and
  240.           navigation systems. Install mission specialists' seats in crew
  241.           cabin. The tail service masts on the mobile launcher platform
  242.           will be closed out for launch.
  243.  
  244.                Enter planned hold at T-11 hours for a duration of 20 hours,
  245.           43 minutes. 
  246.  
  247.                          Launch - 1 Day (Saturday, June 19)
  248.  
  249.                Perform orbiter ascent switch list in crew cabin. During
  250.           this hold at T-11 hours, the orbiter's inertial measurement units
  251.           will be activated and kept in the "warm up" mode and film will be
  252.           installed in the numerous cameras on the launch pad. In addition,
  253.           safety personnel will conduct a debris walkdown and the pad sound
  254.           suppression system water tank will be filled.
  255.  
  256.                The Rotating Service Structure will be moved to the park
  257.           position during this hold at about 11:00 a.m.
  258.  
  259.                Final stowage of experiments into the SPACEHAB module will
  260.           be conducted and flight crew equipment stowage will commence.
  261.  
  262.                Resume countdown. Install time critical flight crew
  263.           equipment and perform the pre-ingress switch list. Start fuel
  264.           cell flow-through purge.
  265.  
  266.                Activate the orbiter's fuel cells. Configure communications
  267.           at Mission Control, Houston, for launch. Clear the blast danger
  268.           area of all non-essential personnel and switch Endeavour's purge
  269.           air to gaseous nitrogen.
  270.  
  271.                             Launch Day (Sunday, June 20)
  272.  
  273.                Enter planned one-hour built-in hold at the T-6 hour mark.
  274.  
  275.                Launch team verifies there are no violations of launch
  276.           commit criteria prior to cryogenic loading of the external tank.
  277.           Clear pad of all personnel.
  278.  
  279.                Resume countdown. Loading the external tank with cryogenic
  280.           propellants is scheduled to begin at 1:13 a.m.
  281.  
  282.                Complete filling the external tank with its flight load of
  283.           liquid hydrogen and liquid oxygen propellants. Perform open loop
  284.           test with Eastern Space and Missile Center and conduct gimbal
  285.           profile checks of orbital maneuvering system engines.
  286.  
  287.                Perform inertial measurement unit preflight calibration and
  288.           align Merritt Island Launch Area tracking antennas.
  289.  
  290.                Wake flight crew at 3:03 a.m.
  291.  
  292.                Enter two-hour hold at T-3 hours.
  293.  
  294.                Closeout crew and ice inspection team proceeds to Launch Pad
  295.           39-B. Crew departs Operations and Checkout Building for the pad
  296.           at 6:08 a.m.
  297.  
  298.                Resume countdown at T-3 hours. Complete closeout
  299.           preparations in the white room and cockpit switch configurations.
  300.  
  301.                Flight crew enters orbiter. Astronauts perform air-to-ground
  302.           voice checks with Mission Control, Houston. Close Endeavour's
  303.           crew hatch. Begin Eastern Space and Missile Center final network
  304.           open loop command checks.
  305.  
  306.                Perform hatch seal and cabin leak checks. The white room is
  307.           closed out and the closeout crew moves to fallback area. Primary
  308.           ascent guidance data is transferred to the backup flight system.
  309.  
  310.                Enter planned 10-minute hold at T-20 minutes.
  311.  
  312.                NASA Shuttle Test Director conducts final briefing.
  313.  
  314.                Resume countdown. Transition orbiter onboard computers to
  315.           launch configuration and start fuel cell thermal conditioning.
  316.           Close orbiter cabin vent valves. Backup flight system transitions
  317.           to launch configuration.
  318.  
  319.                Enter last planned hold at T-9 minutes.
  320.  
  321.                Launch Director and Mission Management Team complete final
  322.           polls for launch. Make any necessary adjustments to hold and
  323.           final count to account for last evaluations of EURECA spacecraft
  324.           location.
  325.  
  326.                Resume countdown.
  327.  
  328.           Start automatic ground launch sequencer (T-9:00 minutes)
  329.           Retract orbiter crew access arm (T-7:30)
  330.           Start mission recorders (T-5:30)
  331.           Start Auxiliary Power Units (T-5:00)
  332.           Arm SRB and ET range safety safe and arm devices (T-5:00)
  333.           Start liquid oxygen drainback (T-4:55)
  334.           Start orbiter aerosurface profile test (T-3:55)
  335.           Orbiter transfers to internal power (T-3:30)
  336.           Start MPS gimbal profile test (T-3:30)
  337.           Pressurize liquid oxygen tank (T-2:55)
  338.           Begin retraction of the gaseous oxygen vent arm (T-2:55)
  339.           Fuel cells to internal reactants (T-2:35)
  340.           Pressurize liquid hydrogen tank (T-1:57)
  341.           Deactivate SRB joint heaters (T-1:00)
  342.           LPS go for start of orbiter automatic sequence (T-0:31 seconds)
  343.           Ignition of Shuttle's three main engines (T-6.6 seconds)
  344.           SRB ignition and liftoff (T-0)
  345.  
  346.           ZDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDD?
  347.           3           SUMMARY OF HOLDS AND HOLD TIMES FOR STS-57          3
  348.           @DDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDY
  349.  
  350.           NOTE: The countdown reflects a target T-0 about 5 minutes prior
  351.           to the assessed actual liftoff time. A rendezvous calibration
  352.           period will be allowed for final determinations of the location
  353.           of the EURECA spacecraft. Any necessary adjustments to the count
  354.           will be made in the final built-in hold at T-9 minutes.
  355.  
  356.           T-TIME ------- LENGTH OF HOLD ---- HOLD BEGINS ---- HOLD ENDS 
  357.  
  358.           T-27 hours --- 8 hours ---------- Thurs., 6:30 pm - Fri., 2:30 am
  359.           T-19 hours --- 4 hours ----------- Fri., 10:30 am - Fri., 2:30 pm
  360.           T-11 hours --- 20 hrs., 43 mins. - Fri., 10:30 pm - Sat., 7:13 pm
  361.           T-6 hours ---- 1 hour ------------ Sun., 12:13 am - Sun., 1:13 am
  362.           T-3 hours ---- 2 hours ----------- Sun., 4:13 am -- Sun., 6:13 am
  363.           T-20 minutes - 10 minutes -------- Sun., 8:53 am -- Sun., 9:03 am
  364.           *T-9 minutes - 10 minutes -------- Sun., 9:14 am -- Sun., 9:24 am
  365.  
  366.           ** This hold likely will be extended beyond the normal 10 minutes
  367.           to reflect the exact launch time based on the latest assessments
  368.           of the location of the EURECA spacecraft.
  369.  
  370.           ZDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDD?
  371.           3                    CREW FOR MISSION STS-57                    3
  372.           @DDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDY
  373.  
  374.           Commander (CDR) Ron Grabe
  375.           Pilot (PLT) Brian Duffy
  376.           Payload Commander (MS1) David Low
  377.           Mission Specialist (MS2) Nancy Sherlock
  378.           Mission Specialist (MS3) Jeff Wisoff
  379.           Mission Specialist (MS4) Janice Voss
  380.  
  381.           ZDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDD?
  382.           3          SUMMARY OF STS-57 LAUNCH DAY CREW ACTIVITIES         3
  383.           @DDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDDY
  384.  
  385.           (Sunday)
  386.           3:03 a.m.      Wake up
  387.           3:33 a.m.      Breakfast
  388.           4:03 a.m.      Free Time
  389.           5:28 a.m.      Weather briefing (CDR, PLT, MS2)
  390.           5:28 a.m.      Don flight equipment (MS1, MS3, MS4)
  391.           5:38 a.m.      Don flight equipment (CDR, PLT, MS2)
  392.           6:08 a.m.      Depart for launch pad 39-B
  393.           6:38 a.m.      Arrive at white room and begin ingress
  394.           7:53 a.m.      Close crew hatch
  395.           9:38 a.m.      Launch (June 20, 1993)
  396.  